Cabling first, because everything else sits on top of it
Structured cabling means a permanent system: fixed cables from patch panels in a comms room out to labelled outlets around the floor, tested and documented as a whole. It isn't the same as running a few cables where they happen to be needed. The difference shows up two years later, when somebody moves a desk or traces a fault, and the answer is a labelled port instead of an afternoon of guesswork.
The standards governing that cabling cap a horizontal copper run at 90 metres of fixed cable between panel and outlet, with 100 metres allowed once the patch leads at each end are counted. That number decides more office layouts than people expect. On a large floor plate, or a tenancy spanning two floors, it can mean a second comms position, which is a landlord and fit-out conversation rather than a shopping decision.
Power changed the rest. Access points, cameras, door controllers and desk phones draw power from the same cable that carries their data, which puts the load on the switch: enough ports, enough power budget across all of them at once, and somewhere cool to live. What to cable, then, is a question of what will plug in over the life of the tenancy, not what plugs in on day one.
- Two outlets at every desk position, and more desk positions than you currently have people.
- Every meeting room: the display position, the table, and the booking panel outside the door.
- Every access point, marked on the reflected ceiling plan with the lights and sprinklers.
- Every camera, door reader and electric lock, which run over the same cabling and switches.
- Spare capacity in the containment itself, for the cables nobody has thought of yet.
The fit-out sequence decides what is possible
Cabling is first-fix work. It goes in while partitions are still studs, before boarding and before the ceiling grid closes. Once the finishes are complete, the same route means either lifting ceiling tiles across half a floor or accepting surface trunking down a glass partition, and nobody who has seen the second option asks for it twice.
A sequence that works: agree the floor layout, draw containment and cable routes onto it, pull cables at first fix, let partitions and ceilings close, terminate outlets and mount access points at second fix, then test, label and document. The awkward part is the first step, because desk layouts are rarely final when cabling has to start, which is the argument for cabling more positions than the plan shows. Everything else living above a ceiling wants cable in that same first fix: lighting control, occupancy sensing, meeting room panels, access control and AV. Treating them as one low-voltage package instead of four procurements that meet for the first time on site is most of what office automation involves.
What a Dubai commercial tower decides for you
Offices here are handed over in very different states. Shell and core gives you a bare slab, a landlord's riser and an incoming supply position. Category A adds raised floor, suspended ceiling and base build lighting, plus a ceiling void already holding chilled water pipework, fan coil units, ducting and sprinklers. A unit left fitted by a previous tenant arrives with cabling nobody can vouch for.
Whatever the state, surveying a commercial unit is largely surveying the building around it, and buildings differ unpredictably. Two towers on the same road can take opposite positions on slab penetrations and on who may work in the riser. Settle the points below with building management before a design is drawn, because a route that turns out to need approval is a two-week problem in week one and a much larger one on installation day.
- Where the landlord's riser and telecom entry point sit, and how a cable gets from there into your unit.
- Whether a containment route already exists, or has to be created and approved.
- Whether penetrations through fire-rated walls or floor slabs are permitted, and how they must be sealed.
- The usable ceiling void depth once pipework, fan coil units, ducting and sprinklers are accounted for.
- Permitted working hours, service lift booking, and what is required for work touching common areas.
The comms room is a room, not a cupboard
The most common false economy in a fit-out is the space allocated to the network. A rack needs clearance front and back, not just a footprint on a drawing. It needs air, because a cabinet of switches delivering power over every port runs warm all day, and a sealed cupboard turns that into a slow reliability problem that presents as random reboots instead of an obvious fault.
Position matters as much as contents. Reasonably central, so the 90 metre limit is not fighting you at the far corners. Close to where the incoming service arrives. Not the route to a store cupboard, because a room people walk through is a room where cables get knocked. In a tenancy spanning two floors the usual answer is a main room with a secondary cabinet upstairs linked through the riser, decided at design stage because it affects power and containment on both floors.
- Floor area for the rack with front and rear access, and a door that opens fully.
- Ventilation or dedicated cooling, sized for a cabinet that runs warm continuously.
- A dedicated power circuit, and a UPS able to hold switches, firewall and phone system through an interruption.
- Spare ports and rack units, a lockable door, and no water pipework running above the rack.
Wi-Fi is a capacity problem before it is a coverage problem
Most offices that complain about Wi-Fi have signal everywhere. What they lack is capacity: enough access points, spread far enough apart and tuned low enough that forty people on video calls aren't all competing for the same airtime. Coverage is easy to demonstrate on a phone and easy to sell. Capacity is what people actually experience at eleven on a Tuesday morning.
An office floor is a difficult radio environment in specific ways. Glass partitions reflect, and plasterboard is nearly transparent to radio, so signal carries much further than it usefully should and access points interfere with one another. The 2.4 GHz band that older devices and building equipment still rely on is congested before you add anything, and in a tower it is congested with the neighbours' networks too. The 5 GHz band gives more room and more speed at the cost of range through solid construction, which argues for more access points running at lower power.
Where those access points go belongs on the ceiling plan next to the lights and sprinklers, agreed with the fit-out team and cabled at first fix. Deciding it on installation day, after ceilings are closed, is how an office ends up with an access point sitting on top of a cupboard. Our Wi-Fi and networking page sets out how that survey works.
Separating the traffic, and why one flat network stops being enough
A VLAN runs several logically separate networks over one physical cabling system. The cable and the switch are shared, but a device on one network cannot reach devices on another unless somebody deliberately allows it. Nothing extra gets installed to achieve this. It's configuration, and it is much of what separates an office network from a large home network.
The separations that earn their place are consistent. Desk phones on their own network, so voice is prioritised and a heavy file transfer does not turn into a broken call, which is a large part of why an office telephone system belongs in the same design as the network. Cameras and recording on their own, since continuous video is heavy predictable traffic. Building systems, access control, lighting and AV on their own, because they are long-lived devices that rarely receive updates and should not be reachable from a visitor's laptop. Guests isolated entirely.
One Dubai-specific note. Security camera work here is regulated by SIRA (opens in a new tab), and the applicable requirements depend on the premises and its use, which makes the camera scope a separate conversation with its own approvals. It is worth starting early, because it affects where recording equipment sits and therefore what the network has to carry.
What goes wrong in offices that were never designed
The faults that bring us into an existing office are rarely exotic. They are usually several of the following at once.
- A consumer router and a couple of unmanaged switches serving thirty desks on one flat network.
- Switches daisy chained under desks because there were never enough outlets, each an undocumented failure point.
- A patch panel with no labels, so every change becomes a process of elimination.
- Access points mounted wherever a cable already existed, which is rarely where coverage was needed.
- Network, phones and cameras bought from three suppliers who first speak to each other on go-live day.
Test it, label it, then write it down
Testing is the item most often skipped and the easiest to insist on. Every cabled link should be tested to the standard of the cable class installed, with the results handed over as a document you keep. It costs a day and removes the cabling from the list of suspects for years. Documentation matters as much: outlet labels matching panel labels, a floor plan showing each outlet, a rack elevation and the network plan. An office changes IT providers more often than it changes cabling, and the handover pack is what stops each change costing a week of rediscovery.
The order to make the decisions in
Most office network problems began as sequencing problems, and they are far cheaper to avoid than to unpick.
- Confirm what the building allows and where its services arrive, before the design is drawn.
- Fix the comms room location, then check it against the 90 metre limit at the furthest corner.
- Agree the floor layout well enough to place outlets, then cable for more positions than it shows.
- Put access point positions on the ceiling plan and cable them at first fix.
- Specify phones, cameras and AV alongside the network, then test, label and document before anyone moves in.
In short
None of this is difficult engineering. An office network works when the unglamorous parts happen in order: cable to more places than you need while the ceiling is open, give the equipment a proper room with air and power, design the wireless around the building instead of around a product, and keep the traffic separated so one busy device can't spoil a call. Get those right and the network stops being something anyone in the office thinks about. If you are planning a fit-out, start with a survey of the unit and an early conversation with building management, which our Wi-Fi and networking page describes.
Common questions
Structured cabling is a planned permanent system: fixed cables from patch panels to labelled outlets, installed to a standard, tested as a whole and documented. Running cables ad hoc gets a device online today but leaves nothing behind, so no labels, no test results and no spare capacity. The cost difference at installation is modest. Two years later it is the difference between changing a patch lead and tracing cable through a ceiling.
Two per desk position is the usual working answer, and the more important number is how many positions you cable at all. Layouts change and teams grow, so cabling only today's desks is how an office ends up with switches daisy chained on the floor. Cable positions you don't yet occupy, and add outlets for meeting rooms, access points, cameras, door readers, printers and displays.
Not well. Wireless is how people connect, but the access points themselves have to be cabled, and so do cameras, door controllers, desk phones, printers and anything fixed. An office with no structured cabling is one where every access point is limited to wherever a cable happens to exist, which is a common cause of poor coverage. Treat wireless as the last layer of a cabled network, not a replacement for one.
A VLAN lets one physical cabling system carry several logically separate networks. Phones, cameras, building systems, staff devices and guests each get their own, and traffic does not cross between them unless it is deliberately allowed. Small offices need it for the same reasons large ones do: a guest device should never reach the camera recorder or the door controller, and voice needs priority so calls stay clean during a large upload. It costs configuration time, not hardware.
